시작일 | 종료일 | 건설회사 | 설비회사 | 프로젝트 | 비고 |
---|---|---|---|---|---|
2024-11-01 | 2024-03-01 | Hyundai Eng America, INC | Joongwon Atlanta, LLC | HL-GA Battery Project(UT Bldg, etc) | In Progress |
2024-05-01 | 2024-12-31 | HJ Shipbuilding & Construction Co., Ltd | Dongbu NTech Co., Ltd | Incheon International Airport's Second Office
| Completed |
2023-12-20 | 2025-01-31 | Samsung Engineering Co., Ltd | JUNGDO Co.,Ltd | Songdo P5 Samsung Biologics Duct Corporation | In Progress |
2023-12-01 | 2026-02-08 | LG Energy Solution | Joongwon Atlanta, LLC | LG Ensol / Honda JV Project OH, USA
| In Progress |
2023-11-27 | 2025-05-30 | Hyundai Engineering | Joongwon Atlanta, LLC | SK Battery America Phaes 3 | In Progress |
2022-11-07 | 2023-12-31 | KCC Engineering & Construction Co., Ltd | JUNGDO Co.,Ltd | Pyeongtaek Technology Building 2 (Win-Win Cooperation Building 2) | Completed |
2022-08-10 | 2022-12-27 | Dongbu Construction Co., Ltd | Dongbu NTech Co., Ltd | Incheon International Airport Stage 4 T2 Long-Term Parking Building | Completed |
2022-07-25 | 2024-05-01 | Dongbu Construction Co., Ltd | Kim and Lee | Hyundai Goyang Deokeun Knowledge Industry Center | Completed |
2022-06-06 | 2024-08-30 | LG Energy Solution | JOONGWOON ATLANTA,LLC | LG / GM ULTium Cells Phase 2 Project TN, USA | Completed |
2022-05-13 | 2022-12-31 | HJ Shipbuilding & Construction | Dongbu NTech Co., Ltd | 19-Hae-00 Project Facilities Construction | Completed |
2022-02-08 | 2022-12-31 | Hyundai E&C | Seongma Enterprise Co., Ltd | Sejong Naver Data Center | Completed |
2021-05-31 | 2022-05-31 | SK E&C | WONBANG TECH USA INC | SK Battery America Phaes 2 | Completed |
2020-11-05 | 2022-05-31 | Halla Construction Co., Ltd | Samwoo E&C Co., Ltd | Jongro Office Complex | Completed |
2020-02-17 | 2021-02-29 | SYS-CON, LLC | Nissi. Inc | SK Battery America Phaes 1 | Completed |
2019-11-28 | 2020-09-30 | CJ Logistics Co., Ltd. | Samwoo E&C Co., Ltd | Amore Pacific Beauty 3rd Plant Equipment Installation | Completed |
2019-11-11 | 2020-12-31 | S&I Co., Ltd. | GS Neotek Co., Ltd | LCE Changwon 1Factory Advancement Project Extinguisher (Phase 1) | Completed |
2019-11-11 | 2020-12-31 | S&I Co., Ltd. | Sungma Enterprise Co., Ltd | LCE Changwon 1Factory Advancement Project Extinguisher (Phase 2) | Completed |
2019-05-03 | 2021-01-31 | CJ Logistics Co., Ltd. | Samwoo E&C Co., Ltd | Kangbuk Samsung Hospital Center for Future Medicine | Completed |
2019-04-22 | 2020-01-15 | Halla Construction Co., Ltd. | YounChang Engineering Co., Ltd | Seoul National Univeristy Smart Campus | Completed |
2019-03-25 | 2020-01-31 | Samsung Engineering Co. Ltd. | Hansung Cleantech Co., Ltd | Samsung Electronics E-PJT Green Area 4 Construction (Phase 2) | Completed |